Plan Submittal and Review Process
- The Applicant must submit a “Plan Review Application” accompanied with the associated plans.
- CUD will review the submitted plans at CUD’s Plan Review Meeting which meets every Thursday morning. Items must be submitted by 10:00 a.m. on Monday to qualify for review or submitted items will generally be reviewed the following Thursday. CUD will endeavor to provide a timely response which usually occurs within 14 business days following review.
- If it is determined that public main line extensions or upgrades to the existing main line are required, a digital CAD file of your plans must be submitted to cudengineering@cudrc.com for the engineering design to be completed once preliminary plans have been approved by local planning commissions. The applicant must submit the “Developer Agreement for Extension of Water Service” form. Engineering fees and inspection fees will need to be paid to CUD at this time.
- The applicant must submit a completed “Meter Application and Fixture Count” form (digital entry preferred) to CUD’s Engineering Department for tap fee calculation, proper meter sizing, and approval. The completed “Meter Application and Fixture Count” form and a PDF copy of the mechanical/plumbing plans and plumbing schedule may be submitted to cudengineering@cudrc.com or in person at CUD’s Engineering Building. CUD will review the submitted “Meter Application and Fixture Count” form and the PDF copy of the plumbing plans for calculation of the tap fee. Please allow a minimum of 14 business days for review and calculation. Once completed, the approved Meter Application will be sent back to the contact email address provided. Please bring the approved Meter Application and payment for the tap fee to the Customer Service Department to sign up for service.